This schedule is a best estimate of cycle dates through March 2010. It should be noted that startup and shutdown dates can be altered by elements not under the control of Operations, such as storms or unexpected maintenance. As much as possible, Operations will hold to a schedule of a startup on Thursday, 38 days of operation, then a shutdown on Sunday. The shutdown will be followed by a 10 day maintenance period. Please note that the cycle which begins in September is interrupted twice. Also note the schedule does not conform to the Thursday/Sunday convention for the September and January cycles. We will update this schedule if further adjustments become necessary.

JANUARY 6 - JANUARY 28 OPERATING
JANUARY 29 - FEBRUARY 11 SHUTDOWN
FEBRUARY 12 - MARCH 22 OPERATING
MARCH 23 - APRIL 8 SHUTDOWN
APRIL 9 - MAY 17 OPERATING
MAY 18 - MAY 27 SHUTDOWN
MAY 28 - JULY 5 OPERATING
JULY 6 - JULY 22 SHUTDOWN
JULY 23 - AUGUST 30 OPERATING
AUGUST 31 - SEPTEMBER 9 SHUTDOWN
SEPTEMBER 10 - SEPTEMBER 23 OPERATING
SEPTEMBER 24 - OCTOBER 4 SHUTDOWN
OCTOBER 5 - OCTOBER 23 OPERATING
OCTOBER 24 - OCTOBER 25 SHUTDOWN
OCTOBER 26 - OCTOBER 31 OPERATING
NOVEMBER 1 - NOVEMBER 11 SHUTDOWN
NOVEMBER 12 - DECEMBER 20 OPERATING
DECEMBER 21 - JANUARY 4 SHUTDOWN
JANUARY 5 - FEBRUARY 12 OPERATING
FEBRUARY 13 - FEBRUARY 24 SHUTDOWN
FEBRUARY 25 - APRIL 4 OPERATING
APRIL 5 - APRIL 14 SHUTDOWN
  
  